In my machine (7FA.05) having FSR SPLIT & DLN SPLIT. this both splits values (in %) are divided by P1, P2, P3 & Q. Below values were taken from one of my prior working days: For FSR split #P1-11.7/P2-12.6/P3-32.7/Q-4.6. During this time unit in PRE SELECT LOAD MODE for 150MW with gas fuel firing.
For DLN split #P1-19.0/P2-20.5/P3- 53.0/Q-7.5.
Any one please give clear answer for above one, because of i am newer for this one. even i searched my plant control document also, but i didn't get clear answer for above one. I want come to know what is meaning of FSR SPLIT & DLN SPLIT with its origin and why them were divided to P1, P2, P3 & Q.
For DLN split #P1-19.0/P2-20.5/P3- 53.0/Q-7.5.
Any one please give clear answer for above one, because of i am newer for this one. even i searched my plant control document also, but i didn't get clear answer for above one. I want come to know what is meaning of FSR SPLIT & DLN SPLIT with its origin and why them were divided to P1, P2, P3 & Q.