Recent content by Bijitkb

  1. B

    Queries regarding GE Gas Turbines Frame VI MarkVIe

    GE Frame VI & Mark VIe Gas Turbine Generator (GTG) spreads was found on the higher sides during loading (approx. 21 MW+). As recorded,GTG spreads at 22.4 MW load were:  Spread-1 = 45.4 deg C  Spread-2 = 32.1 deg C  Spread-3 = 31.1 deg C.  M/C was Shutdown for GTG-2 High...