In our site, we have turbogenerators for the production of electricity (max 7MW). One in service which is synchronized with the national network and others in stand-by. The objective of our study is to evaluate the risks during operation of a machine exceeding the limit of the hours of march (requires revision MI and HGPI), the tolerances of the risks will be shared with the service exploitation
Thank you for advising us for:
-the paramount parameters to watch out for the actions to be performed on the instrumentation parts (jet pump, exhaust transmitters, valves)
and for the mechanical part which is essential because our rotor exceeds their hours of service (vibration, paper temperatures, axial displacement ...)
Thank you for helping us find the potential risks and actions we should be doing to ensure safe operation until the major inspection.
-Evaluation of the risks for the operation of a turbogenerator exceeds the limit of hours of operation.
-The actions and strategy to adopt for the control and monitoring of these PGT.
Thank you for advising us for:
-the paramount parameters to watch out for the actions to be performed on the instrumentation parts (jet pump, exhaust transmitters, valves)
and for the mechanical part which is essential because our rotor exceeds their hours of service (vibration, paper temperatures, axial displacement ...)
Thank you for helping us find the potential risks and actions we should be doing to ensure safe operation until the major inspection.
-Evaluation of the risks for the operation of a turbogenerator exceeds the limit of hours of operation.
-The actions and strategy to adopt for the control and monitoring of these PGT.