Hello everyone,

In one of our LSTK project of Gas Turbine, 15MW,BHEL (bharat heavy electricals Ltd) make turbine & generator with Mark-VIe control, the contractor has supplied the Turbine and the generator separately, and waiting for the foundation/skid to be ready in install both. But unfortunately it may take at least one year more to install. In such a situation, what kind of maintenance to be done both on the GT & the alternator? Where in the official guidelines can we find on this?

Regards
 