    turbine gas frame 6B house load test

    We have a GT frame 6 engine with Mrk V control system, baseload at 30 MW load. we plan to do houseload testing with load rejection at 75% baseload. at the time of load rejection, the 52G will be released and the turbine FSNL with a load of 0.2 MW. the governor mode will automatically change from...
  2. Abdul majid bakti

    mark V control system <S >

    We have Mark V turbine control system for our Frame 6 GAS turbine. after rebooting, the <S> processor, it is not coming to A7 state. it is showing A6 state. Kindly suggest some check points.