We have a Berthold UniProbe LB 490 radiometric level transmitter installed on our pool reactor vessel containing carbamate solution. Recently, we have been experiencing recurring IOP alarms for the level detector on our DCS.
The steps taken so far:
- Loop integrity checked multiple times.
-...
We have a GE Frame 9E (PG 9171E) gas turbine, operation controlled by speedtronic MARK VI controller running on Permeate Low-BTU Gas.
Recently, we observed a transient spike in Exhaust Spread-1(132°C) during normal operation. Upon investigation it was found that one of the 24 exhaust...