I have TPS SYSTEM consist of 5 GUSes (Dell GX1,running Windows NT operating system ), HPM , HM and SMM.
I contact with Honeywell inc. to get an offer to upgrade it to Experion PKS stations.
Honeywell offered me the following :
1- SW upgrades for all my plant TPS system at current release( TPN from Rel 610 to Rel 682 , TPS-GUS from Rel 203 to Rel 420 ).
2- 5 new Experion Stations (to replace existing 5 GUS stations)
3- 1 new Redundant (ESVT) Experion server.
4- The FTE infrastructure (2 FTE Switches) to connect the new nodes.
5- 1 Cabinet (to install the servers and switches) equipped with KVM for user interface.
6- 1 year SESP.
I want to Know every point in this offer and if this offer is Good or i must upgrade to another system.
I contact with Honeywell inc. to get an offer to upgrade it to Experion PKS stations.
Honeywell offered me the following :
1- SW upgrades for all my plant TPS system at current release( TPN from Rel 610 to Rel 682 , TPS-GUS from Rel 203 to Rel 420 ).
2- 5 new Experion Stations (to replace existing 5 GUS stations)
3- 1 new Redundant (ESVT) Experion server.
4- The FTE infrastructure (2 FTE Switches) to connect the new nodes.
5- 1 Cabinet (to install the servers and switches) equipped with KVM for user interface.
6- 1 year SESP.
I want to Know every point in this offer and if this offer is Good or i must upgrade to another system.