Wind Turbine SCADA cabinet delay for single GE turbine

I have a delay of 2 months for a SCADA cabinet for a single GE wind turbine. The wind turbine provides 90K in utility savings a month for our manufacturing plant, so this is a big hit. Is it possible to develop a temporary solution that would allow us any time & cost savings for the operation of the turbine? Would any solutions pass snuff with Ameren?


Talking with GE Vernova, the HMI they are sending is out of Vietnam, if that helps.
 