Is there any standard method for restoring process loads after power failure.
In the plant(Oil refinery) there are 10Nos motor loads which are performing different operation asper process needs. Customer needs to restore this loads automatically after a power failure. Please give some inputs on process load restoration,i am very new to process project.
We are planning to suggest a priority based load restoration for this. Where operator shall give process load priority and time delays from HMI and a controller performs restoration operation. Will this be suitable..?