For all control master, currently i have problem in load sharing new turbine. We build a new power plant for cement plant, 2x35 MW coal fired by using Siemens Turbine. Existing plant operates Steam Turbine Generator, STG A & B, while new turbine STG C & D will be controlled by new plant. The grid to cement plant is only 1, and it comes from existing plant, which currently run manually since from information, operators need to adjust the frequency in response of load changing. We try making load sharing in DCS for new turbine C & D only without involved STG A & B? Let say normal operation load to 100 MW, where 60 MW will be handled by new turbine STG C & D, and the rest by existing turbine. If anytime the load decrease to let say 80 MW, then we will maintain the power from existing at 40 MW, means it's new plant will adjust its power down to 40 MW. If the load continue decrease to 50, then both new STG will contribute only for 10 MW. But in case the required power is above the normal load to peak load, it's existing plant need to adjust to cover the requirement. So, when the load is over the max normal load, i.e : 120, then it's existing STG which will adjust, means STG C & D will be maintain at 60 MW, while STG A & B will be up to 60 MW. If the load is decrease but still above the max normal load, i.e: 110, then still operator will need adjust STG A & B only to 40 MW.
The questions are :
1. Is it possible to do such operation and load sharing? Siemens insist that such thing is impossible. According to them, operation will only work when load sharing involve whole 4 STG.
2. Is it dangerous to do above operation, especially to new Siemens turbine ?
Sorry if my question looked so silly since i'm just newbie and still zero in a power plant.
Really appreciated to any response.
The questions are :
1. Is it possible to do such operation and load sharing? Siemens insist that such thing is impossible. According to them, operation will only work when load sharing involve whole 4 STG.
2. Is it dangerous to do above operation, especially to new Siemens turbine ?
Sorry if my question looked so silly since i'm just newbie and still zero in a power plant.